Thanks for the excellent question!
For CTPP 2000, FHWA contracted for the TAZ-UP software directly, but
this time, it is part of the FHWA Interagency Agreement with the Census
Bureau.
For THIS ROUND OF CTPP, the Census Bureau Geography Division is hiring a
contractor to develop the software for TAZ (and TAD) delineation. The
CB has asked me not to mention the contractor, as they may still be in
negotiations.
Just as a reminder: The Base TAZs are going to be limited to block
equivalencies. Originally, we thought that TAZs were going to be
defined in 2009 and would have allowed for modifications to segments,
but this process was shifted to 2011, which is closer in time to the
CTPP small area tabulation (using ACS from 2006-2010). One of the major
factors in moving this task to 2011 was that the CB raised their cost
estimate for the software and incorporation into TIGER by a very high
margin in summer 2008. (I don't remember exactly, but it was something
on the order of $100,000 more than the original estimate).
Elaine Murakami
206-220-4460
________________________________
From: ctpp-news-bounces(a)chrispy.net
[mailto:ctpp-news-bounces@chrispy.net] On Behalf Of James Galvin
Sent: Wednesday, December 02, 2009 1:10 PM
To: ctpp-news(a)chrispy.net
Subject: RE: [CTPP] Memo to Census Bureau regarding delineation business
rules
Penelope:
I found the following in my read through and added a correction. I
don't remember reviewing the first. Is this a RFP for mapping software
to be made available top MPO's (and DOT'S)?
Page 4, Section IV
B. Ancillary (non-Census) Data
Users must be allowed to import and display the following kinds of data
files for use as a
reference when delineating TAZ entities:
Jim
James J. Galvin, Jr. AICP
Dover/Kent County MPO
302.387.6030 (ph)
________________________________
From: ctpp-news-bounces(a)chrispy.net
[mailto:ctpp-news-bounces@chrispy.net] On Behalf Of Weinberger, Penelope
Sent: Wednesday, December 02, 2009 2:28 PM
To: ctpp-news(a)chrispy.net
Subject: [CTPP] Memo to Census Bureau regarding delineation business
rules
Hi All,
The Census Bureau asked us to refine this document to help them with
their software development effort. There was a three step process and
this is step two. Step three will be the formal version of the attached
memo, due to Census Bureau in early 2010. At this time we are seeking
input on this memo for the formal version. Please reply directly to me
with your comments.
Please reply by January 8th, 2010
Thanks!
Penelope Weinberger
CTPP Program Manager
AASHTO
202-624-3556
http://ctpp.transportation.org/home/default.htm